Case Study - Bell Creekbank

Bell Creekbank - 5025 Creekbank Road
Owner/developer: Bell Canada / H&R Reit
General Contractor: Aecon
Architect: Bregman & Hamann Architects
Electrical Consultant: Lapas Engineering
Start / End Date:  August 2007 - October 2008

Bell's Creekbank Phase III project is a new construction office space project in Mississauga.  The construction of this five-storey office building began with two levels of underground parking in August 2007.

This project institutes environmental design that includes the following landscape elements: high albedo paving, high efficiency irrigation, and dark sky compliant lighting which conform to LEED.

Interborough Electric was awarded the underground electrical services for Enersourse and for communication, as well as, temporary incoming services, parking lot lighting and the civil work for the underground services.